Strata Schemes Management Act 2015 No 50

Part 11
Division 2
Section 201

Final report | Section 201

(1)  A building inspector appointed to carry out a final inspection is to carry out a final inspection of the building work, and provide a final report, not earlier than 21 months and not later than 2 years after the completion of the building work.

(2)  The final report must—

(a)  be in the form and contain the matters prescribed by the regulations for the purposes of this section, and

(b)  without limiting paragraph (a), identify defective building work identified in the interim report that has not been rectified, and

(c)  identify any defective building work arising from rectification of defective building work previously identified in the interim report, and

(d)  specify how the defective building work identified in the report should be rectified.

(3)  The final report must not contain matters that relate to defective building work not identified in the interim report, other than work arising from rectification of defective building work identified in the interim report.

© State of New South Wales Department of Customer Service. For current information go to www.nsw.gov.au.

Disclaimer: Reproduced from the Strata Schemes Management Act 2015 . This website does not give legal advice or other professional advice. You should seek legal or other professional advice before acting and not rely on any of the content on this website.

didn't find what you are looking for?

Try searching for It

Hello!

Drop us a message!