Wednesday, September 30, 2020

Strata Schemes Management Act 2015 No 50

Part 6
Division 6
Section 132

Rectification where work done by owner | Section 132

(1)  The Tribunal may, on application by an owners corporation for a strata scheme, make either of the following orders if the Tribunal is satisfied that work carried out by or for an owner or occupier on any part of the parcel of the scheme has caused damage to common property or another lot—

(a)  an order that the owner or occupier performs the work or takes other steps as specified in the order to repair the damage,

(b)  an order that the owner or occupier pay to the owners corporation or the owner of the lot a specified amount for the cost of repairs of the damage and any associated costs, including insurance and legal costs.

(2)  An amount payable by an owner or occupier to an owners corporation under this section is payable, and may be recovered, under this Act as if it were an amount of unpaid contributions.

Note.

Section 86 provides for the recovery of unpaid contributions.

© State of New South Wales Department of Customer Service. For current information go to www.nsw.gov.au.

Disclaimer: Reproduced from the Strata Schemes Management Act 2015 . This website does not give legal advice or other professional advice. You should seek legal or other professional advice before acting and not rely on any of the content on this website.